Sales and Construction Update

Despite the many twists and turns we’ve faced in 2020, the team at Watermark has been able to make significant progress throughout the soon-to-be-completed Armstrong Creek community.

Below the ground in Stage 8A, sewer and drainage works are now complete and water works are in progress. The electrical and NBN installation will begin once these works are complete, with Titles expected in this Stage in the last quarter of 2020.

Meanwhile in Stages 11A and 8B, electrical and NBN infrastructure has been installed and works will soon begin on concreting, ahead of Titles in October and November respectively.

As Watermark moves towards completion in 2021, homes are being constructed all over the already close-knit community, with future residents eager to meet their new neighbours and begin their lives in Armstrong Creek.